CompTIA Project+ Practice Questions

Question 1
Before the final product is launched, the marketing team suggests presenting the product to a
predefined set of customers who may be able to provide relevant insight for improvement. Which
of the following would the project manager MOST likely conduct?
A. Workshop
B. Brainstorming
C. Stand-up
D. Focus group


Question 2
Which of the following would be the MOST important consideration for call center personnel
accepting customer orders and payments on a website?
A. Intellectual property protection
B. Branding restrictions
C. Personally identifiable information security
D. Multifactor authentication


Question 3
A project manager is performing the initial risk assessment on a risk that has been highlighted.
Which of the following steps should be executed as part of this assessment?

A. Identifying project communication methods
B. Determining the impact of risks
C. Rewriting the scope of work
D. Defining key project resources


Question 4
A project manager experiences issues that may delay the project from moving toward production
release due to the stakeholder's refusal to sign off. The stakeholder thinks this step should be
done by someone else. Which of the following should the project manager review?

A. RBS
B. RACI
C. WBS
D. CCB


Question 5
A project manager has been assigned to a new project and is informed that a similar issue was
resolved on another project last year. Which of the following should the project manager do
NEXT?
A. Determine the solution design.
B. Review existing artifacts.
C. Define the preliminary scope statement.
D. Identify the stakeholders.


Question 6
In the kickoff meeting, a project manager announced the project will use a tool to store
documents, artifacts, and any other data relevant to the project. The tool will perform version
control, maintain retention data, and archive destruction or historical information. Which of the
following is being described?

A. Record management system
B. Project dashboard
C. Backlog
D. Wiki knowledge base


Question 7
A project manager prepared a project closeout report for stakeholders, clients, and team
members. Which of the following describes the benefits of the project closeout report?
A. It highlights team members who underperformed.
B. It allows the project manager to explain and justify poor outcomes.
C. It shows the project manager's perspective on the project.
D. It helps the project manager to determine what worked well and what can be improved.


Question 8
The PMO has just reduced a project's priority from 4 to 12 out of 22. As a result of the project
prioritization change, the highly skilled resources have been reassigned to higher priority
projects. The issue has been recorded on the issue log, and the change in resources has been
included on the change control log. Which of the following should the project manager do
NEXT?

A. Inform the project team that mandatory overtime is required for the remainder of the project.
B. Conduct an impact assessment to determine the effects on the project baselines.
C. Encourage the project sponsor to use referent power to get the project's priority elevated.
D. Accept the change and cite the resource reduction whenever there is a schedule slippage.


Question 9
A project manager wants to know the billable hours an employee has spent on a project. Which
of the following can the project manager use?

A. Project status report
B. Calendaring tools
C. Time-tracking tools
D. Task board


Question 10
A risk that equipment may be delayed develops during a project. The project team is
experiencing:

A. scope creep.
B. a change.
C. an issue.
D. a work-around.






Project+ Answer Key

Question 1) D.

Question 2) C.

Question 3) B.

Question 4) B.

Question 5) B.

Question 6) A.

Question 7) D.

Question 8) B.

Question 9) C.

Question 10) C.